Progress

Expand the tabs to view Kotilinga Kshetram progress for a particular Year.

2021
      April
  • Acquired a Steer and a Calf.
  • On Ugadi day we inaugurated the Sri Venkateswara Gokulam.
      March
  • Built the Cow Barn and Shed.
      February
  • Topographic survey happened by Civil Engineering Firm.
      January
  • Sri Venkateswara Gokulam project was announced to the public for funds.
2020
      August
  • Hired Civil Engineering Firm for grading.
      July
  • Structural Engineering Firm completed Architectural Design Development documents.
      June
  • Structural Engineering contract signed.
      April
  • The Engineering firm submitted the initial conceptual design drawings.
      March
  • Sri Narayani Amma of Sri Puram blessed the project and suggested to acquire a cow to Graze on the Kotilinga Kshetram area for sanctification.
  • Acquired and paid for 157 major Banalingas from Omkareswar and made arrangements for supply of 1 Crore 2-inch Banalingas from the same vendor.
      February
  • Structural Engineer was identified, interviewed.
      January
  • The Project was announced to the public. Public support was very enthusiastic and close to $ 2 million were Pledged.
  • We procured 3 Crystal Lingas (Sadasiva, Chadramouliswara & Chendeswara).